Mechanic's Lien Guide

Illinois Mechanic's Lien Guide

Lien deadlines, notice requirements, and filing procedures for contractors, subcontractors, and suppliers in Illinois.

Illinois Lien Deadlines

Preliminary Notice

Not required for most projects

Not required for most projects. However, notice must be given within 60 days of starting work by subcontractors working on an owner-occupied single-family residential project without a direct contract with the owner.

Mechanic's lien

4 months

Must be filed within 4 months of last work. Enforcement must be initiated within 2 years of last work. Mechanic's liens cannot be extended in Illinois.

Calculate your Illinois Mechanics Lien Deadline

Your project

DISCLAIMER: These deadlines are pulled from recent lien laws, but you should consult a lien expert or lawyer to understand the deadlines specific to your situation.

Illinois deadlines

Showing deadlines for a Subcontractor. Deadlines can vary by role.

Enter your project dates on the left to calculate exact deadline dates.

Preliminary Notice

Generally not required; on single-family owner-occupied residence, 60 days from starting work

Enter project dates to calculate

Notice of Intent to Lien

90 days from last furnishing

Enter project dates to calculate

Mechanics Lien Filing

4 months after completion of work

Enter project dates to calculate

Enforcement (foreclosure)

2 years after completion of work

Calculated once you record the lien

Unpaid-balance state: your lien may be limited to the amount the owner still owes the general contractor when notice is received.

Illinois Lien Guide

Preliminary Notice & Notice of Intent

Preliminary Notice: A 60-day notice for subcontractors and suppliers working on an owner-occupied single-family residential project without a direct contract with the owner. Notice of Intent to Lien: Parties without a direct contract with the project owner must provide a Notice of Intent to Lien within 90 days of last furnishing labor or materials to the project in order to have mechanic's lien rights.

Who Can File a Mechanic's Lien

Contractors, subcontractors, laborers, and suppliers are entitled to mechanic's lien rights in Illinois.

Who Gets the Notice

Notice is given to the project owner and general contractor.

Information Required

Information needed to file a mechanic's lien in Illinois includes: - Project owner’s name - Property description - Labor/materials description - Amount owed - Work dates - Claimant’s info

Illinois Public Works

In Illinois, a mechanic's lien on public works projects is not available. Subcontractors and suppliers can file suit on a payment bond and also have the option of a lien on unexpended project funds. A written notice of bond claim is required within 180 days of last work. A suit cannot be filed more than 1 year after last work.

Illinois Lien Statutes

Protect Your Cash Flow

Filing a mechanic's lien is the last resort. Billd helps you get paid faster so you can focus on building.

Get Started
← All State Lien Guides

The Billder's Bulletin

Construction finance intelligence, delivered monthly.

Join thousands of construction executives getting the Billder's Bulletin.